The Newlands
Interchange Project
| This material has been produced by the Royal Society of New Zealand (RSNZ)
under contract to the Ministry of Education. It has been written to assist teachers
and schools in their delivery of the technology/ hangarau curriculum statements.
The project is jointly coordinated by personnel from the Technology Education
New Zealand (TENZ)
and National Association of Māori Mathematicians, Scientists and Technologists
(NAMMSAT) networks. Monitoring and evaluation of the material is carried out
by a national project advisory group. |
Introduction
Newlands interchange is at the top of the Ngauranga Gorge.a steep grade of
about one in twelve, over a short 1.8km length of State Highway One situated
8km North of Wellington City.
The Newlands Interchange Project was a huge civil engineering challenge which
involved removal of an existing set of traffic lights and conversion of
the T-intersection with the State Highway into a grade-separated interchange
- the aim being to reduce both the amount of traffic congestion and the
number of vehicle accidents.
The construction phase began in January 1997 and was completed, with a minimum
disruption to road users, two months ahead of schedule in August 1998.
The cost of $16.7 Million was $600,000 below allocation.
This is a overview of the development of the project.
The need
The Ngauranga Gorge section of State Highway 1 carries large volumes of commuter
traffic between Wellington City and Northern areas including Johnsonville, Newlands,
Porirua and the Kapiti Coast, as well as being the main route for travellers
North from Wellington. The traffic flow is approximately 60,000 vehicles per
day and this is growing at approximately 3% each year. About 13,000 vehicles
a day use Newlands Road , which previously formed a signalised T-intersection
with the State Highway. The very high morning and evening weekday peak directional
flows on State Highway 1 resulted in considerable peak hour congestion and an
unacceptably high number of traffic accidents.
A number of options were considered during the investigation and design phases
to resolve the problems at this intersection. The Interchange proposal was finally
adopted after extensive consultation and assessment of the traffic, economic
and environmental issues.
Major groups
involved in the project
Client: Transit New Zealand
Consultant: Opus International Consultants
Main Contractor: Fulton Hogan Ltd.
Disciplines involved in the consultancy work for the investigation, design
and construction phases included engineers, scientists, planners, draughting
staff and lawyers.
Key features
of the new interchange:
- The Newlands overbridge providing grade-separation of the interchange
- A fourth lane northbound to the Newlands off-ramp
- Upgrading of signage
- Separate provision for pedestrians and cyclists, including two subways
- Upgrading of highway lighting
- Extensive reshaping and trimming back of the steep rock bluffs on both
sides of the gorge
- Strengthening and rehabilitation of an existing major culvert carrying
the Ngauranga stream and buried up to 17m below the intersection
- Extensive landscape rehabilitation and revegetation
Specific
features and innovations relating to the project
- Adoption of a formal Partnering Charter at the beginning of the construction
phase to foster a team approach between the client, consultant, contractor
and other parties involved. This was one of the first applications of this
approach on a Transit New Zealand project.
- A very high standard of temporary traffic control to maximise the safety
of workers and motorists whilst also minimising disruption to the public
- Cuttings up to 50m high in highly fractured rocks with residential properties
at the top of these slopes and a very busy highway at the bottom required
risk assessment and decision analysis to optimise costs and risks
- Adoption of a steel box girder form for the bridge superstructure to enable
erection with minimum traffic disruption
- Architectural input into the bridge design to produce an aesthetic structure
in a location where the bridge has high visual significance as a gateway structure
to Wellington
- A demanding site which is exposed to high seismicity and in close proximity
to the Wellington fault, with variable ground conditions across the site required
a range of special features to provide significant earthquake resistance
- The use of new technology zinc/aluminium thermal metal spray for corrosion
protection of the bridge box steel girders to provide an expected life to
first maintenance in excess of 40 years
- Resolution of potential conflicts between vehicles, cyclists and pedestrians
through, for example, provision of subways
- Strengthening and rehabilitation of the major culvert carrying a stream
beneath the intersection using an innovative system employing internal sleeving
and grouting
- Measurement of noise and light levels prior to commencement of construction
to provide a benchmark against which to compare these conditions as they arose
both during and after construction, and monitoring of noise levels during
construction
- Extensive landscaping to ensure revegetation and to blend the interchange
structures into the natural landscape and environment
- Extensive community consultation throughout the duration of the project,
including regular meetings with community representatives to provide information
and promptly address any complaints as they arose.
 |
The design
and construction of the overbridge
Ngauranga Gorge is generally acknowledged as the gateway to Wellington , and
consequently an overbridge was seen as having the potential to act as a natural
entrance feature. A subway under the highway had been considered during the
scheme assessment phase but the tender submitted did not meet acceptable geometric
standards.
The architectural and urban design theme developed for the bridge led to the
proposal of three alternative design concepts:
- a conventional multi-span bridge
- a through-arch bridge
- a cable-stayed bridge
Public consultation undertaken by Transit New Zealand favoured the through-arch
bridge option. This was therefore adopted for further development and preliminary
design to sufficient detail to confirm structural feasibility and develop accurate
costings.
Site constraints reduced the arch-bridge options to three tied arch options
which, while feasible were assessed to cost in excess of $5 million - approximately
double the cost of a conventional multi-span bridge. The arch concept for the
bridge was therefore discarded.
Options for a multi-span bridge were constrained by Transit New Zealand's requirements
that traffic flows at peak times be maintained on the State Highway without
disruption and piers intruding into the State Highway be minimised.
Consequently only two-span options were considered, in both steel and concrete.
Incrementally launched concrete box girder or T-beam continuous superstructures
were not considered to be economic or viable, due to the superstructure depth
required. An option using large precast U-beams was also considered. For the
spans required, unit handling weights of about 80 tonnes were estimated. Availability
of cranes to handle such units of which there are only a few in New Zealand
was considered likely to constrain construction programming and inhibit the
competitiveness of pricing.
The final solution adopted was a continuous superstructure consisting of four
parallel trapezoidal steel box girders with a cast in-situ composite concrete
deck. Of particular significance was the ease with which this could be erected
by craning box girder sections into position with the maximum handling weight
reduced to less than 45 tonnes.
The fact that the Newlands Interchange site is close to the Wellington fault
posed major practical difficulties in designing for 'near fault' earthquake
events. A feature of the developed design was the substantial anchorage
required to stabilise the abutments against the very large forces. In
order to achieve a practical design for the eastern approach embankment
and the western abutment, potential outward movements of 50mm were accepted
for these elements under design earthquake intensity response. The bridge
is 'base isolated' for earthquakes at the pier and two abutments and is
supported on lead rubber bearings. These will effectively act as shock
absorbers in a major earthquake and protect the bridge from major damage.
Within financial constraints, and in recognition of its siting, an emphasis
was placed on the aesthetics of the bridge. A sculptural quality and visual
impact were sought through treatments to achieve visual lightness of the bridge
superstructure, contrasted by visual heaviness of the supporting pier and abutments.
Special lighting was also adopted to emphasise the bridge at night.
As a bridge spanning a high traffic volume state highway, the need to minimise
future maintenance was an important consideration. The site is exposed to wind
blown salt spray and so new technology for corrosion protection was utilised
and visible exposed concrete surfaces treated with a clear anti-graffiti coating
system .
The project gained a high level of community support . In view of the proximity
of residential areas to the construction site, monitoring of noise levels was
an important activity and restrictions on the timing of certain works imposed.
A high standard of traffic control was maintained at all times to protect staff,
the travelling public and to minimise delays.
Benefits
from the new Interchange
- The project meets Transit New Zealand's main objective of providing a safer
and more efficient highway. It has resulted in:
- Reduced delays, improved safety and an improved level of service for both
highway users and the local community
- Improved pedestrian and cyclist facilities
- A benefit/cost ratio in excess of six (ie for every dollar spent on the
project the benefits are expected to exceed six times that amount)
- Predicted accident savings estimated at $1.3 million per year adding up
to a total saving of $12 million over a 25 year period
- Travel time and vehicle operating benefits of approximately $70 million
over the same period of time due to the elimination of traffic signals
- An estimated reduction of 9% in CO2 emissions
The project won the 1999 NZ Contractor's Federation Award for projects over
$3 million and was a finalist in the Infrastructure category of the 1999 Institution
of Professional Engineers of New Zealand (IPENZ) Engineering Excellence Awards.
This has been adapted from material produced by . The case study
will be published as part of the EG series - a resource designed to support
Technology in the New Zealand Curriculum. EG is a joint initiative by IPENZ,
The Royal Society of New Zealand and Technology Education New Zealand (TENZ).
For more information contact:
publications@rsnz.govt.nz
|