HomeNewsAboutCommunitiesSearchSchoolsInteractGatewayHelp
Technology


Case studies of technological practice

The Newlands Interchange Project

Next page: The design | Benefits

This material has been produced by the Royal Society of New Zealand under contract to the Ministry of Education. It has been written to assist teachers and schools in their delivery of the Technology/Hangarau curriculum statements. The project is jointly co-ordinated by personnel from the Technology Education New Zealand (TENZ) and National Association of Māori Mathematicians, Scientists and Technologists (NAMMSAT) networks. Monitoring and evaluation of the material is carried out by a national project advisory group.
Other material

Introduction

Newlands interchange is at the top of the Ngauranga Gorge – a steep grade of about one in twelve, over a short 1.8km length of State Highway 1 situated 8km north of Wellington City.

(PHOTO: Looking South down the Gorge)

The Newlands Interchange Project was a huge civil engineering challenge which involved removal of an existing set of traffic lights and conversion of the T-intersection with the State Highway into a grade-separated interchange - the aim being to reduce both the amount of traffic congestion and the number of vehicle accidents.

(Newlands Interchange: Layout)

The construction phase began in January 1997 and was completed, with a minimum disruption to road users, two months ahead of schedule in August 1998. The cost of $16.7 million was $600,000 below allocation.


Overview of the development of the project

The need

The Ngauranga Gorge section of State Highway 1 carries large volumes of commuter traffic between Wellington City and northern areas including Johnsonville, Newlands, Porirua, and the Kapiti Coast, as well as being the main route for travellers north from Wellington. The traffic flow is approximately 60,000 vehicles per day and this is growing at approximately 3 percent each year. About 13,000 vehicles a day use Newlands Road, which previously formed a signalised
T-intersection with the State Highway. The very high morning and evening weekday peak directional flows on State Highway 1 resulted in considerable peak hour congestion and an unacceptably high number of traffic accidents.

A number of options were considered during the investigation and design phases to resolve the problems at this intersection. The Interchange proposal was finally adopted after extensive consultation and assessment of the traffic, economic, and environmental issues.

Major groups involved in the project

Client:

Transit New Zealand
Consultant:

Opus International Consultants
Main Contractor:

Fulton Hogan Ltd

Disciplines involved in the consultancy work for the investigation, design and construction phases included engineers, scientists, planners, draughting staff, and lawyers.


Key features of the new interchange:
  • The Newlands overbridge providing grade-separation of the interchange
  • A fourth lane northbound to the Newlands off-ramp
  • Upgrading of signage
  • Separate provision for pedestrians and cyclists, including two subways
  • Upgrading of highway lighting
  • Extensive reshaping and trimming back of the steep rock bluffs on both sides of the gorge
  • Strengthening and rehabilitation of an existing major culvert carrying the Ngauranga stream and buried up to 17m below the intersection
  • Extensive landscape rehabilitation and revegetation
 

Specific features and innovations relating to the project:
  • Adoption of a formal Partnering Charter at the beginning of the construction phase to foster a team approach between the client, consultant, contractor, and other parties involved. This was one of the first applications of this approach on a Transit New Zealand project.
  • A very high standard of temporary traffic control to maximise the safety of workers and motorists whilst also minimising disruption to the public.
  • Cuttings up to 50m high in highly fractured rocks with residential properties at the top of these slopes and a very busy highway at the bottom required risk assessment and decision analysis to optimise costs and risks.
  • Adoption of a steel box girder form for the bridge superstructure to enable erection with minimum traffic disruption.
  • Architectural input into the bridge design to produce an aesthetic structure in a location where the bridge has high visual significance as a gateway structure to Wellington.
  • A demanding site which is exposed to high seismicity and in close proximity to the Wellington fault, with variable ground conditions across the site required a range of special features to provide significant earthquake resistance.
  • The use of new technology zinc/aluminium thermal metal spray for corrosion protection of the bridge box steel girders to provide an expected life to first maintenance in excess of 40 years.
  • Resolution of potential conflicts between vehicles, cyclists, and pedestrians through, for example, provision of subways.
  • Strengthening and rehabilitation of the major culvert carrying a stream beneath the intersection using an innovative system employing internal sleeving and grouting.
  • Measurement of noise and light levels prior to commencement of construction to provide a benchmark against which to compare these conditions as they arose both during and after construction, and monitoring of noise levels during construction.
  • Extensive landscaping to ensure revegetation and to blend the interchange structures into the natural landscape and environment.
  • Extensive community consultation throughout the duration of the project, including regular meetings with community representatives to provide information and promptly address any complaints as they arose.


Next page: The design | Benefits